Calculating OEE
The Formulas
As described in World Class OEE, the OEE calculation is based on the three OEE Factors: Availability, Performance, and Quality. Here's how each of these factors is calculated.
Availability
Availability takes into account Down Time Loss, and is calculated as:
Availability = Operating Time / Planned Production Time
Performance
Performance takes into account Speed Loss, and is calculated as:
Performance = Ideal Cycle Time / (Operating Time / Total Pieces)
Ideal Cycle Time is the minimum cycle time that your process can be expected to achieve in optimal circumstances. It is sometimes called Design Cycle Time, Theoretical Cycle Time or Nameplate Capacity.

Since Run Rate is the reciprocal of Cycle Time, Performance can also be calculated as:
Performance = (Total Pieces / Operating Time) / Ideal Run Rate
Performance is capped at 100%, to ensure that if an error is made in specifying the Ideal Cycle Time or Ideal Run Rate the effect on OEE will be limited.
Quality
Quality takes into account Quality Loss, and is calculated as:
Quality = Good Pieces / Total Pieces
OEE
OEE takes into account all three OEE Factors, and is calculated as:
OEE = Availability x Performance x Quality
It is very important to recognize that improving OEE is not the only objective. Take a look at the following data for two production shifts.

OEE Factor      Shift 1      Shift 2
Availability      90.0%      95.0%
Performance      95.0%      95.0%
Quality      99.5%      96.0%
OEE      85.1%      86.6%

Superficially, it may appear that the second shift is performing better than the first, since its OEE is higher. Very few companies, however, would want to trade a 5.0% increase in Availability for a 3.5% decline in Quality!

The beauty of OEE is not that it gives you one magic number; it's that it gives you three numbers, which are all useful individually as your situation changes from day to day. And it helps you visualize performance in ** terms - a very practical simplification.
Example OEE Calculation
The table below contains hypothetical shift data, to be used for a complete OEE calculation, starting with the calculation of the OEE Factors of Availability, Performance, and Quality. Note that the same units of measurement (in this case minutes and pieces) are consistently used throughout the calculations.

Item      Data
Shift Length      8 hours = 480 min.
Short Breaks      2 @ 15 min. = 30 min.
Meal Break      1 @ 30 min. = 30 min.
Down Time      47 minutes
Ideal Run Rate      60 pieces per minute
Total Pieces      19,271 pieces
Reject Pieces      423 pieces

Planned Production Time
=
=
= 420 minutes

Operating Time
=
=
= 373 minutes

Good Pieces
=
=
= 18,848 pieces

Availability      =      Operating Time / Planned Production Time
      =      373 minutes / 420 minutes
      =      0.8881 (88.81%)

Performance      =      (Total Pieces / Operating Time) / Ideal Run Rate
      =      (19,271 pieces / 373 minutes) / 60 pieces per minute
      =      0.8611 (86.11%)

Quality      =      Good Pieces / Total Pieces
      =      18,848 / 19,271 pieces
      =      0.9780 (97.80%)

OEE      =      Availability x Performance x Quality
      =      0.8881 x 0.8611 x 0.9780
      =      0.7479 (74.79%)

futurepower (2008-11-17 12:39:22)好资料, 感谢! 方便了兄弟门呀 !!! 以后跟老外讲解这个真的是没有那么麻烦了aaron8 (2008-12-01 16:04:59)多谢啊楼主,对学习怎么用英文说很有用。rexxing (2008-12-04 20:34:41)不错,顶一下。。。。。。。。。。。。。。。

blueatsea 发表于 2011-2-22 03:19:22

多谢啊楼主,对学习怎么用英文说很有用

att0604034142 发表于 2011-4-18 15:10:21

增加了见识啊

kotel 发表于 2021-1-9 16:23:35

自从论坛改版之后,我就已经心灰意冷,对论坛也没抱什么希望了,传说已经幻灭,神话已经终结,留在论坛还有什么意思。没想到,没想到,今天可以再睹楼主的风范,我激动得忍不住就在屏幕前流下了眼泪。是啊,只要在楼主的带领下,论坛就有希望了。我的内心再一次沸腾了,我胸腔里的血再一次燃烧了。

qingefjc 发表于 2021-1-9 16:30:54

你们觉得楼主有我萌吗?`(*∩_∩*)′

lawyer-chen 发表于 2021-1-9 16:34:07

据说云鲸智能的拖地机很不错

菜菜和小 发表于 2021-1-9 16:37:57

十几年的网站了 很不错

海水幽蓝 发表于 2021-1-9 16:52:29

云鲸机器人在哪有卖的

冉朝瀚 发表于 2021-1-9 16:55:20

工业工程已经深深的代入到了各个行业

plmokn29 发表于 2021-1-9 16:58:46

如果你感觉我ID帅气,请粉我
页: [1] 2 3 4
查看完整版本: OEE计算 英文版 _ 工业工程网